8 new military housing units open; South Post total now 55

The construction of eight new military housing units in the South Post Family Housing Area was completed Jan. 27.
PHOTO: Walt Sanders, the Housing Maintenance Inspector, meets with Arlene Rodriguez at the her Families new house on South Post. Photo by Rob Schuette
Walt Sanders, the Housing Maintenance Inspector, meets with Arlene Rodriguez. Rodriguez, her husband, Sgt. 1st Class Ronald Rodriguez, and their Family members have moved into one of the new eight military Family housing units on South Post. (Photo by Rob Schuette)

The addition of these eight homes brings the total of government-owned military housing units on Fort McCoy to 55.

The new housing has been issued to eligible active-duty Soldiers on permanent change of station orders who were on the housing wait list.

This housing project was constructed as a result of funding from the American Recovery and Reinvestment Act (ARRA), also known as stimulus funds. Gohman Construction of St. Joseph, Minn., was the contractor.

The $3.3 million construction project included infrastructure, streets, water and sewer and landscaping.

Carlson Construction of Joliet, Ill., constructed 23 military housing units, completed in the first phase of the project.

PHOTO: A view of several of the new military Family housing units in the South Post area. Photo by Rob Schuette
A view of several of the new military Family housing units in the South Post area. The housing was completed Jan. 27, and eligible military Families are settling into the homes. (Photo by Rob Schuette)

These units, which also were funded with ARRA stimulus funds, were occupied in May 2011.

All 31 housing units in the two projects feature four bedrooms, kitchens, laundries, Family rooms and two-car garages.

Plans are in place to construct additional military Family housing on South Post to satisfy Fort McCoy’s housing requirement of 134 units, as calculated by an Army Housing Market Analysis.

The next project to add military housing on South Post is scheduled for fiscal year 2014, according to the Fort McCoy Family Housing Office.